Energy

PM to open Matarbari coal-fired plant in December: project officials

Will add 600MW to national grid, they said
Photo courtesy: UNB
The first unit of Matarbari coal-fired power plant in Maheshkhali of Cox's Bazar is likely to go into production by this December, adding 600MW of electricity to the national grid.

 

The first unit of Matarbari coal-fired power plant in Maheshkhali of Cox's Bazar is likely to go into production by this December, adding 600MW of electricity to the national grid.

Prime Minister Sheikh Hasina is expected to inaugurate the plant, project officials told reporters this week.

A ship carrying 64,300 tonnes of coal for the Matarbari plant had arrived from Indonesia on June 23.

The 1200MW power plant has been built on 1,414 acres of land in Matarbari and Dhalghata unions of Maheshkhali upazila of Cox's Bazar district.During a recent visit of the area, it was seen that the project implementing company, Coal Power Generation Company Bangladesh Limited (CPGCL), is going ahead with the work of this mega project.

The work of the jetty for the coal discharge with the power plant is almost finished. Vessels have also started sailing at the jetty.Some 13,104 tonnes of coal will be required daily to generate electricity at full scale. Coal discharge jetties and silos have been constructed for this.

Coal required for 60 days has been kept in the huge silos. Vessels with up to 80,000 tonnes capacity can enter the coal jetty. And it will take one and a half to two days to unload the coal from the vessel.

Two separate ash ponds are kept to store ash for a lifetime of 25 years of the power plant. One has an area of 90 acres, another spread over 600 acres. Coal yard has been prepared on 80 acres of land for coal storage.

A loan agreement on the project was signed between the Government of Bangladesh and JICA on June 16, 2014. The project cost has been estimated at Tk 51,800 crores.

Of this, Tk 43,921 crore will be given as project support by JICA and the remaining Tk 7,933 crore will be provided from the own funds of Bangladesh Government and CPGCBL.

According to project sources, 95 percent of the jetty and physical infrastructure work has already been completed and 90 percent of the overall physical infrastructure work has been done.

Executive Director Nazmul Huq, Matarbari coal-fired plant project said that PM Hasina will inaugurate the power plant in December.

"But we want to add 600 MW power from here before inauguration and that will happen. The first unit of the Matarbari coal-fired power plant is scheduled to be commissioned in January 2024, but we expect to be fully operational by this December," he said.

He mentioned that the second unit will be commissioned next July.

However, he said, electricity from both the units will be connected to the national grid.

The executive director mentioned that the project is being worked on by ensuring all necessary measures to prevent environmental pollution.

"The coal will be seen only once when the coal is unloaded from the ship. Then the coal will go directly from the jetty to the plant. It will not pollute the environment," he said.Cox's Bazar Deputy Commissioner Muhammad Shaheen Imran told reporters that the Matarbari Coal Power Project is a priority project of the prime minister.

Comments

PM to open Matarbari coal-fired plant in December: project officials

Will add 600MW to national grid, they said
Photo courtesy: UNB
The first unit of Matarbari coal-fired power plant in Maheshkhali of Cox's Bazar is likely to go into production by this December, adding 600MW of electricity to the national grid.

 

The first unit of Matarbari coal-fired power plant in Maheshkhali of Cox's Bazar is likely to go into production by this December, adding 600MW of electricity to the national grid.

Prime Minister Sheikh Hasina is expected to inaugurate the plant, project officials told reporters this week.

A ship carrying 64,300 tonnes of coal for the Matarbari plant had arrived from Indonesia on June 23.

The 1200MW power plant has been built on 1,414 acres of land in Matarbari and Dhalghata unions of Maheshkhali upazila of Cox's Bazar district.During a recent visit of the area, it was seen that the project implementing company, Coal Power Generation Company Bangladesh Limited (CPGCL), is going ahead with the work of this mega project.

The work of the jetty for the coal discharge with the power plant is almost finished. Vessels have also started sailing at the jetty.Some 13,104 tonnes of coal will be required daily to generate electricity at full scale. Coal discharge jetties and silos have been constructed for this.

Coal required for 60 days has been kept in the huge silos. Vessels with up to 80,000 tonnes capacity can enter the coal jetty. And it will take one and a half to two days to unload the coal from the vessel.

Two separate ash ponds are kept to store ash for a lifetime of 25 years of the power plant. One has an area of 90 acres, another spread over 600 acres. Coal yard has been prepared on 80 acres of land for coal storage.

A loan agreement on the project was signed between the Government of Bangladesh and JICA on June 16, 2014. The project cost has been estimated at Tk 51,800 crores.

Of this, Tk 43,921 crore will be given as project support by JICA and the remaining Tk 7,933 crore will be provided from the own funds of Bangladesh Government and CPGCBL.

According to project sources, 95 percent of the jetty and physical infrastructure work has already been completed and 90 percent of the overall physical infrastructure work has been done.

Executive Director Nazmul Huq, Matarbari coal-fired plant project said that PM Hasina will inaugurate the power plant in December.

"But we want to add 600 MW power from here before inauguration and that will happen. The first unit of the Matarbari coal-fired power plant is scheduled to be commissioned in January 2024, but we expect to be fully operational by this December," he said.

He mentioned that the second unit will be commissioned next July.

However, he said, electricity from both the units will be connected to the national grid.

The executive director mentioned that the project is being worked on by ensuring all necessary measures to prevent environmental pollution.

"The coal will be seen only once when the coal is unloaded from the ship. Then the coal will go directly from the jetty to the plant. It will not pollute the environment," he said.Cox's Bazar Deputy Commissioner Muhammad Shaheen Imran told reporters that the Matarbari Coal Power Project is a priority project of the prime minister.

Comments

মির্জা ফখরুল ইসলাম আলমগীর

মানুষের ধারণা সরকার ইচ্ছা করে নির্বাচন বিলম্বিত করছে: মির্জা ফখরুল

বিএনপির মহাসচিব বলেন, ‘এটি আমার ধারণা নয়। দেশের মানুষের মাঝে ধারণা তৈরি হচ্ছে যে সরকার ইচ্ছাকৃতভাবে নির্বাচন প্রক্রিয়াকে বিলম্বিত করছে। এটা সঠিক নয়। কিন্তু একই সঙ্গে এটা মানুষের মধ্যে আশংকা সৃষ্টি...

১১ মিনিট আগে