Metro rail mock-up coach installed
In order to inform people about the metro rail—a new mode of public transport in Bangladesh, a mock-up of the coach will be displayed.
The display will start at the exhibition and information centre of MRT-6 in Dhaka's Uttara late next month.
There, people will be able to learn about the looks of the inside of the train and the ticket-buying process, MAN Siddique, managing director of Dhaka Mass Transit Company Ltd (DMTCL), told The Daily Star today.
DMTCL, a government-owned company, is implementing the metro rail project. MRT-6 is the route between Uttara Third Phase and Motijeel.
Siddique said they have brought the mock-up coach from Japan on December 26 last year and kept it inside the under-construction exhibition and information center at Uttara's Diabari.
"Today we have unpacked the [mock-up] coach and installed it at the base of the exhibition center so that other incomplete work can be done smoothly," he said.
All work will be completed soon and the mock-up coach will be opened for public in late next month, he said.
Besides, they will set up a mechanism there so that people can have first-hand experiences like how to buy tickets at a station, he added.
Construction work of the Tk 22,000-crore Mass Rapid Transit (MRT Line)-6, which began in 2016, has made 40.36 per cent progress as of January and is expected to be opened to the public on December 16, 2021, coinciding with the golden jubilee of the country's independence.
Once completed, the rail service, which has 16 stations, will be able to carry 60,000 passengers per hour, reducing travel time from Uttara to Motijheel to at least less than an hour from the current two hours.
More than nine kilometres of the 20.10km long viaduct is now visible and work is continuing on the remaining ones.
Meanwhile, the government decided to extend the line—now under construction from Uttara to Motijheel —up to Kamalapur Railway Station so that people can avail the rail service directly from the country's largest railway station.
The topographical survey for it has already been done and now a "social survey" is being conducted. After completing the extesion work, the total length of the rail route would be 21.26km with 17 stations.