Prime Minister Sheikh Hasina yesterday said the government wants to improve the country's road network to boost its socio-economic development. “The more the country's communication network is developed, the greater will be the changes in its socio-economic scenario,” she told the inauguration programme of the Saat Rasta to Holy Family Hospital part of the Moghbazar-Mouchak Flyover at the city's Officers Club.
The Saat Rasta-Holy Family Hospital part of the Moghbazar-Mouchak flyover was plagued with long tailback moments after it was opened to traffic yesterday.
Once built, the 8.70km Moghbazar-Mouchak flyover is set to become a permanent woe for Dhaka, with leading experts describing the Tk 1,219 crore structure as a massive block in the heart of the city. Around a year into the construction work in early 2014, it was detected by sheer chance that the much-hyped flyover was being built on a grossly faulty layout configuration without vital right-turn provisions and had a number of other flaws with serious consequences.
The initial cost of the Moghbazar-Mouchak flyover was Tk 7.73 billion and original completion of the project was December 2014.
The government yesterday increased the building cost of the Moghbazar-Mouchak Flyover Project by Tk 446.20 crore and extended the completion deadline by 18 months.
The Executive Committee of the National Economic Council (Ecnec) has approved revision of the Moghbazar-Mouchak Flyover Project with an extension of 18 months and increased cost of Tk 446.20 crore, raising the overall project cost to Tk 1,218.90 crore.
An out of control bus kills two workers and injured one at the Moghbazar-Mouchak flyover construction site in Dhaka.
The Saat Rasta-Holy Family Hospital part of the Moghbazar-Mouchak flyover was plagued with long tailback moments after it was opened to traffic yesterday.
Prime Minister Sheikh Hasina yesterday said the government wants to improve the country's road network to boost its socio-economic development. “The more the country's communication network is developed, the greater will be the changes in its socio-economic scenario,” she told the inauguration programme of the Saat Rasta to Holy Family Hospital part of the Moghbazar-Mouchak Flyover at the city's Officers Club.
Once built, the 8.70km Moghbazar-Mouchak flyover is set to become a permanent woe for Dhaka, with leading experts describing the Tk 1,219 crore structure as a massive block in the heart of the city. Around a year into the construction work in early 2014, it was detected by sheer chance that the much-hyped flyover was being built on a grossly faulty layout configuration without vital right-turn provisions and had a number of other flaws with serious consequences.
The initial cost of the Moghbazar-Mouchak flyover was Tk 7.73 billion and original completion of the project was December 2014.
The government yesterday increased the building cost of the Moghbazar-Mouchak Flyover Project by Tk 446.20 crore and extended the completion deadline by 18 months.
The Executive Committee of the National Economic Council (Ecnec) has approved revision of the Moghbazar-Mouchak Flyover Project with an extension of 18 months and increased cost of Tk 446.20 crore, raising the overall project cost to Tk 1,218.90 crore.
An out of control bus kills two workers and injured one at the Moghbazar-Mouchak flyover construction site in Dhaka.