Moghbazar flyover

Moghbazar Flyover: Relief, but not much in peak hours

When the afternoon sun was shining down around 2:15pm yesterday, Sagor Hossain started for Farmgate from Shantinagar. He chose that particular time for the journey mainly to avoid the rush-hour traffic.

Moghbazar Flyover / Change to create more chaos

The extended Moghbazar Flyover ramp near Sonargaon Hotel may make the already crammed street even more congested, according to an expert and project officials. Moreover, a 50-metre carriageway deck of the ramp, already built in front of the Bangladesh Film Development Corporation (popularly known as the FDC) at a cost of around Tk 9.5 crore, would now have to be demolished, said a project official.

'Mega' challenge

In the stumbling block of concrete mess at Moghbazar, Minhaz Abedin waits patiently every day, worrying about his unemployed son, something he has been doing for the past three years now.

Moghbazar flyover costlier by Tk 446cr

The government yesterday increased the building cost of the Moghbazar-Mouchak Flyover Project by Tk 446.20 crore and extended the completion deadline by 18 months.

Moghbazar flyover ordeal won’t end soon (video)

What began as the construction of a one-of-a-kind elevated expressway in Dhaka two years ago, the Moghbazar flyover has suffered periods of lags in the making. The traffic situation along the construction site that has turned worse is unlikely to get better until the completion of the structure – not before 2017.

November 7, 2017
November 7, 2017

Moghbazar Flyover: Relief, but not much in peak hours

When the afternoon sun was shining down around 2:15pm yesterday, Sagor Hossain started for Farmgate from Shantinagar. He chose that particular time for the journey mainly to avoid the rush-hour traffic.

June 5, 2016
June 5, 2016

Change to create more chaos

The extended Moghbazar Flyover ramp near Sonargaon Hotel may make the already crammed street even more congested, according to an expert and project officials. Moreover, a 50-metre carriageway deck of the ramp, already built in front of the Bangladesh Film Development Corporation (popularly known as the FDC) at a cost of around Tk 9.5 crore, would now have to be demolished, said a project official.

June 2, 2016
June 2, 2016

'Mega' challenge

In the stumbling block of concrete mess at Moghbazar, Minhaz Abedin waits patiently every day, worrying about his unemployed son, something he has been doing for the past three years now.

January 20, 2016
January 20, 2016

Moghbazar flyover costlier by Tk 446cr

The government yesterday increased the building cost of the Moghbazar-Mouchak Flyover Project by Tk 446.20 crore and extended the completion deadline by 18 months.

August 28, 2015
August 28, 2015

Moghbazar flyover ordeal won’t end soon (video)

What began as the construction of a one-of-a-kind elevated expressway in Dhaka two years ago, the Moghbazar flyover has suffered periods of lags in the making. The traffic situation along the construction site that has turned worse is unlikely to get better until the completion of the structure – not before 2017.