Water bodies vital for Dhaka’s survival

Restore the water body of airport area, solve waterlogging

Rail operations to resume with goods trains tomorrow

Intercity services to resume from August 15, tickets available from 5pm tomorrow

Proper feasibility study a must for railway projects

That Bangladesh Railway (BR) has been a loss-incurring entity for almost a decade is not news.

Rajbari-Tungipara: A lone train operating on Tk 2,110cr line!

Bangladesh Railway had taken up a project in 2010 to bring Tungipara of Gopalganj under the railway network without carrying out any feasibility study.

13 railway projects: Cost overrun up to 260pc, time 9.5 years

Bangladesh Railway in October 2007 took up a project to construct a new station building in Khulna and enhance the operational capacity of the Benapole Station.

Dhaka's rail link restored after nearly 5 hours as workers withdraw blockade

Workers take up position in front of Rail Bhaban to press home demands

Faridpur-Magura Rail Link: Poor monitoring to blame for slow pace

After observing the slow pace of a project under which rail tracks are being laid on a 19km stretch between Faridpur and Magura, a report prepared by a government body has accused the railway authorities of serious lacking in their monitoring.

Padma Bridge Rail Link Project: Railway seeks one-year extension on loan tenure

Bangladesh Railway (BR) is seeking a one-year extension on its loan tenure for the Padma Bridge Rail Link Project as a means to avoid upward cost revisions resulting from hassles in clearing payments after the task is complete.

Eviction without rehabilitation is deeply irresponsible

The need for development cannot override the moral imperative to protect the marginalised

October 23, 2024
October 23, 2024

Water bodies vital for Dhaka’s survival

Restore the water body of airport area, solve waterlogging

August 11, 2024
August 11, 2024

Rail operations to resume with goods trains tomorrow

Intercity services to resume from August 15, tickets available from 5pm tomorrow

July 3, 2024
July 3, 2024

Proper feasibility study a must for railway projects

That Bangladesh Railway (BR) has been a loss-incurring entity for almost a decade is not news.

July 2, 2024
July 2, 2024

Rajbari-Tungipara: A lone train operating on Tk 2,110cr line!

Bangladesh Railway had taken up a project in 2010 to bring Tungipara of Gopalganj under the railway network without carrying out any feasibility study.

October 3, 2023
October 3, 2023

13 railway projects: Cost overrun up to 260pc, time 9.5 years

Bangladesh Railway in October 2007 took up a project to construct a new station building in Khulna and enhance the operational capacity of the Benapole Station.

July 16, 2023
July 16, 2023

Dhaka's rail link restored after nearly 5 hours as workers withdraw blockade

Workers take up position in front of Rail Bhaban to press home demands

July 10, 2023
July 10, 2023

Faridpur-Magura Rail Link: Poor monitoring to blame for slow pace

After observing the slow pace of a project under which rail tracks are being laid on a 19km stretch between Faridpur and Magura, a report prepared by a government body has accused the railway authorities of serious lacking in their monitoring.

July 4, 2023
July 4, 2023

Padma Bridge Rail Link Project: Railway seeks one-year extension on loan tenure

Bangladesh Railway (BR) is seeking a one-year extension on its loan tenure for the Padma Bridge Rail Link Project as a means to avoid upward cost revisions resulting from hassles in clearing payments after the task is complete.

April 29, 2023
April 29, 2023

Eviction without rehabilitation is deeply irresponsible

The need for development cannot override the moral imperative to protect the marginalised

April 29, 2023
April 29, 2023

Railway tracks bent again in Brahmanbaria

Due to excessive heat, the rail line in Brahmanbaria's Sadar upazila has been bent again. According to the Brahmanbaria Railway Station master Rafiqul Islam, the incident happened on Saturday around 10:30am in the Dariapur area.