The government is continuing to ramp up the power generation capacity even though the electricity demand did not increase as per projection, putting an additional price burden on consumers, said energy experts.
At least 15 percent of the country’s 71 independent power producers were sitting idle for 80 percent of the time last fiscal year, raising questions about their need.
World Bank recommendations on capacity development should be followed properly
Increased power outages causing suffering among ordinary people
Aminbazar in Dhaka to Gopalganj 400KV double circuit line, considered one of the major power transmission lines in the country, is ready to transmit electricity.
Thirty-five percent of all capacity payments the government made to independent power producers (IPPs) over the last three years went to two private companies and a joint venture.
The government is continuing to ramp up the power generation capacity even though the electricity demand did not increase as per projection, putting an additional price burden on consumers, said energy experts.
At least 15 percent of the country’s 71 independent power producers were sitting idle for 80 percent of the time last fiscal year, raising questions about their need.
World Bank recommendations on capacity development should be followed properly
Increased power outages causing suffering among ordinary people
Aminbazar in Dhaka to Gopalganj 400KV double circuit line, considered one of the major power transmission lines in the country, is ready to transmit electricity.
Thirty-five percent of all capacity payments the government made to independent power producers (IPPs) over the last three years went to two private companies and a joint venture.